THE PROBLEM

The owner believed low throughput was mainly an effort issue. Investigation showed the line itself required stop-start operation and restricted operator productivity.

IMMEDIATE ACTION

Staffing, break cover, attendance controls, shift handovers and downtime escalation were introduced before major CAPEX.

THE REDESIGN

A heavy-duty, belt-fed, dual-sided picking system was developed to investment-ready stage for 600+ tonnes per month.